Instruction Manual PCD 650
41
Hence calibration in % Saturation of DO should be carried out first. This is
described in the following section.
3.1.6 Prepare the Meter for Calibration
Before starting calibration, make sure the meter is in the appropriate
measurement mode.
For pH
Connect the pH probe to the BNC connector of the meter.
Be sure to remove the protective electrode storage bottle or rubber cap of the
electrode before calibration or measurement. If the electrode has been
stored dry, wet the electrode in clean water for 10 minutes before calibrating
or taking readings to saturate the pH electrode surface and minimize drift.
Wash your electrode in clean water after use, and store in electrode storage
solution. If storage solution is not available, use pH 4.01 or 7.00 buffer
solution. Do not reuse buffer solutions after calibration. Contaminants in the
solution can affect the calibration, and eventually the accuracy of the
measurements.
It is recommended that you perform at least a 2-Point Calibration using
standard buffers that adequately cover the expected measurement range,
prior to measurement.
For Ion
Connect the ISE to the BNC connector of the meter.
Remove plastic protective cap of ISE. Briefly rinse the electrode with clean
clean water to remove any residues. Rinse ISE before and after each
calibration or sample measurement to avoid cross-contamination. Ensure that
you use new or fresh standard solutions during calibration. Do not reuse Ion
standard solution as it may be contaminated and affect the calibration and
accuracy of measurements.
For Conductivity
Connect the conductivity probe with built-in temperature sensor into the 8-pin
connector of the meter.
For best results, select a standard value close to the sample value you are
measuring. Alternatively use a calibration solution value that is approximately
2/3 the full-scale value of the measurement range you plan to use. For
example, in the 0 to 2000 µS conductivity range, use a 1413 µS solution for
calibration.
Perform calibration for all measurement ranges to ensure the highest
accuracy throughout all measurement range. Calibration for different ranges
is indicated in the Technical Specifications table on page 5, calibration
factors are applied only to their respective ranges
If you are measuring in solutions with Conductivity lower than 100 µS/cm or
TDS lower than 50 ppm, calibrate the meter at least once a week to get good
accuracy. If you are measuring in the mid ranges and you wash the electrode
in de-ionized water and store it dry, calibrate the meter once a month. If you
take measurements at extreme temperatures, calibrate at least once a week.